NASA’s Space Launch System Green Run leaves open possibility of Artemis 1 launch this year

The core stage for the first flight of NASA’s Space Launch System rocket is seen in the B-2 Test Stand during a hot fire test Jan. 16, 2021, at NASA’s Stennis Space Center near Bay St. Louis, Mississippi. Credits: NASA.

A week ago today NASA ran the Space Launch System Green Run test meant to be the last test of the four massive Shuttle era RS-25 engines and core stage before being shipped to the Kennedy Space Center in preparation for the planned Artemis 1 launch later this year. The Space Launch System, NASA’s massive deep space rocket is designed to propel astronauts to the Moon in a few years.

The four RS-25 engines fired for a little more than one minute and generated 1.6 million pounds of thrust.
The four RS-25 engines fired for a little more than one minute and generated 1.6 million pounds of thrust. Credit: NASA.

The test didn’t go quite as NASA planned, though the engines lit up, ran for over a minute and then shut down. They were supposed to run for a full eight minutes, simulating an actual launch burn to orbit.

NASA Artemis 1 mission logo
NASA Artemis 1 mission logo. Credit: NASA.

The good news is that NASA feels they might have enough data to move forward. They admitted that they used very conservative parameters for the test which is why the automated systems shut down the engines a minute into the test.

They will continue to examine the data while still trying to keep on schedule and launching the uncrewed Artemis 1 mission around the Moon late this year.

NASA has yet to determine if it will do the test over again.

Watch the Artemis I Green Run engine hot fire test

NASA January 21 update

For the Green Run hot fire test on Jan. 16, NASA set out to acquire test data to support 23 detailed verification objectives. To satisfy the objectives, hot fire test data is used in combination with analysis and testing that has already been completed. These detailed verification objectives are used to certify the design of the Space Launch System rocket’s core stage.

The preliminary assessment indicates that the data acquired met the goals for a number of the 23 objectives, such as those related to activities prior to engine ignition. The initial assessment also indicates that data acquired partially met the goals for several additional of the 23 objectives related to simultaneous operations of four RS-25 engines.

This infographic explains more about the core stage and its massive liquid hydrogen and liquid oxygen tanks that hold more than 700,000 gallons of propellant.
This infographic explains more about the core stage and its massive liquid hydrogen and liquid oxygen tanks that hold more than 700,000 gallons of propellant. Credit: NASA.

NASA and its industry partners, Boeing and Aerojet Rocketdyne, are continuing to assess the extensive data from the test. As part of the planned near-term activities, they will complete the final assessment determining which objectives were fully met and which ones were partially met. They also are evaluating the value of acquiring additional test data and a longer run time to augment the existing analyses and data.

Currently, the SLS core stage can still be loaded with propellant and pressurized 20 more times for a total of 22 cycles. Rocket stages like the core stage are designed to be loaded with cryogenic propellant and pressurized a specific number of times. These are called cryogenic loading cycles. Before Green Run testing began, SLS had allocated nine cryogenic cycles for testing at NASA’s Stennis Space Center in Bay St. Louis, Mississippi and has used two of those during the hot fire and wet dress rehearsal, with seven cryogenic cycles remaining for additional testing. For the Artemis I Iaunch, NASA is preserving 13 of the remaining 20 cryogenic loading cycles. These can be used for multiple launch attempts, a wet dress rehearsal on the launch pad, and other activities that require propellant loading and tank pressurization.

One of the critical activities that must happen before either another hot fire test or launch is drying and refurbishment of the engines. That activity is underway. NASA is continuing to inspect the core stage and its RS-25 engines on the B-2 test stand, and initial inspections indicate the hardware is in excellent condition.

Hardware inspection and data assessment will continue and will inform NASA’s decision on whether to conduct a second Green Run test or proceed with shipping the core stage to Kennedy for integration with other SLS hardware in the Vehicle Assembly Building.

About Marc Boucher

Boucher is an entrepreneur, writer, editor & publisher. He is the founder of SpaceQ Media Inc. and Executive Vice President, Content of SpaceNews. Boucher has 25+ years working in various roles in the space industry and a total of 30 years as a technology entrepreneur including creating Maple Square, Canada's first internet directory and search engine.